Milestones (Projections)

  • August 2008 – hired as primary consultant on project
  • February 2009 – Government of Canada and Government of Ontario announce financial support of the BWG Leisure Centre in the amount of $16.4 M.
  • March 2009 – Schematic Design Approved at Town Council
  • June 2009 – Tender for Location Site Works prepared
  • August 2009 – groundbreaking on site works to commence
  • November 2009 – Tender for facility construction prepared
  • February 2010 – Tender for facility construction awarded
  • March 2010 – facility construction commences
  • January 2012 – facility opening projected